You are viewing a free preview of this lesson.
Subscribe to unlock all 10 lessons in this course and every other course on LearningBro.
Network analysis (also called Critical Path Analysis or CPA) is a project management technique that enables businesses to plan, schedule, and manage complex projects. It identifies the sequence of activities that determines the minimum project duration and highlights where delays will affect completion.
Before constructing or interpreting a network diagram, you need to understand these terms:
| Term | Definition |
|---|---|
| Activity | A task or job that consumes time and resources (represented by an arrow in activity-on-arrow diagrams) |
| Node | A circle representing the start or end of an activity. Contains the event number, Earliest Start Time (EST), and Latest Finish Time (LFT) |
| Duration | The time required to complete an activity |
| Predecessor | An activity that must be completed before another can begin |
| Earliest Start Time (EST) | The earliest point at which an activity can begin (calculated by a forward pass) |
| Latest Finish Time (LFT) | The latest point at which an activity can finish without delaying the project (calculated by a backward pass) |
| Critical path | The longest sequence of dependent activities through the network — it determines the minimum project duration |
| Float (total float) | The amount of time an activity can be delayed without delaying the overall project |
| Dummy activity | A dotted arrow with zero duration, used to show logical dependencies without consuming time |
Each node in an activity-on-arrow diagram is divided into three sections:
Identify every activity, its duration, and its predecessors.
Worked Example: Launching a New Product
| Activity | Description | Duration (weeks) | Predecessor |
|---|---|---|---|
| A | Market research | 4 | — |
| B | Product design | 6 | A |
| C | Supplier sourcing | 3 | A |
| D | Prototype development | 5 | B |
| E | Packaging design | 3 | C |
| F | Testing | 4 | D |
| G | Marketing campaign | 6 | C |
| H | Production setup | 3 | E, F |
| I | Launch | 2 | G, H |
Start at node 1 (time 0) and work forwards. At each node, the EST is the highest value from all incoming paths.
| Node | Calculation | EST (weeks) |
|---|---|---|
| 1 | start of project | 0 |
| 2 | via A: 0 + 4 | 4 |
| 3 | via B: 4 + 6 | 10 |
| 4 | via C: 4 + 3 | 7 |
| 5 | via D: 10 + 5 | 15 |
| 6 | max(via E: 7 + 3 = 10, via F: 15 + 4 = 19) | 19 |
| 7 | max(via G: 7 + 6 = 13, via H: 19 + 3 = 22) | 22 |
| 8 | via I: 22 + 2 | 24 |
At any node with multiple incoming paths, take the highest EST — the activity cannot start until every preceding activity is finished.
Minimum project duration: 24 weeks
Start at the final node and work backwards. At each node, the LFT is the lowest value from all outgoing paths.
Subscribe to continue reading
Get full access to this lesson and all 10 lessons in this course.