You are viewing a free preview of this lesson.
Subscribe to unlock all 10 lessons in this course and every other course on LearningBro.
When a contract is breached, the innocent party is entitled to a remedy. The primary remedy in English contract law is damages (monetary compensation). In exceptional cases, equitable remedies such as specific performance and injunction may be available. This lesson examines the principles governing the assessment of damages, the rules on remoteness and mitigation, the distinction between liquidated damages and penalty clauses, the equitable remedies, and consumer remedies under the Consumer Rights Act 2015.
Damages are the primary remedy for breach of contract. The aim is to put the innocent party in the position they would have been in had the contract been performed — the "expectation interest." This is sometimes called the "performance interest."
The innocent party can recover expectation loss — the financial benefit they expected to receive from the contract.
For example, if A contracts to buy goods from B for £500, and B fails to deliver, and the goods would have been worth £800, A's expectation loss is £300 (the profit they would have made).
Alternatively, the innocent party can recover reliance loss — the expenditure they have incurred in reliance on the contract.
In Anglia Television Ltd v Reed [1972], the claimant television company hired an actor for a film. The actor repudiated the contract. The company could not find a replacement and abandoned the project. They could not prove what profit they would have made (expectation loss), so instead they claimed the wasted expenditure (reliance loss) — the money spent on directors, designers, and production costs before the actor was hired. The Court of Appeal held that reliance loss was recoverable, including pre-contractual expenditure, provided it was reasonably within the contemplation of the parties.
Note: A claimant cannot claim both expectation and reliance loss for the same item — this would amount to double recovery. However, they can choose whichever measure is more favourable.
Where defective work has been performed, the court must decide between two measures of damages:
| Measure | Explanation |
|---|---|
| Cost of cure | The cost of putting the defect right |
| Difference in value | The difference between the value of what was promised and the value of what was received |
In Ruxley Electronics and Construction Ltd v Forsyth [1996], a swimming pool was built 18 inches shallower than specified (6 feet instead of 7 feet 6 inches). The cost of rebuilding the pool was £21,560, but the difference in value was nil (the pool was perfectly usable). The House of Lords awarded £2,500 for loss of amenity — the cost of cure was disproportionate, and the difference in value did not reflect the claimant's legitimate interest.
Not all losses caused by a breach are recoverable. The innocent party can only recover losses that are not too remote — i.e., losses that were within the reasonable contemplation of the parties at the time of contracting.
The leading case on remoteness is Hadley v Baxendale (1854). A mill shaft broke and the mill owners sent it to the defendants for delivery to an engineer for repair. The defendants delayed the delivery, and the mill was idle for longer than necessary. The mill owners claimed for lost profits.
Baron Alderson established the two-limb test:
| Limb | Rule | Application |
|---|---|---|
| Limb 1 | Losses arising naturally from the breach — in the ordinary course of things | The "normal" consequences of the breach |
| Limb 2 | Losses that were in the reasonable contemplation of both parties at the time of contracting, as a probable result of the breach | "Special" losses that the defendant knew about because of special knowledge |
The mill owners' claim failed under Limb 2 — the carrier did not know that the mill would be idle while the shaft was being repaired (the mill might have had a spare shaft).
Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949]:
The defendants sold a boiler to the claimants (a laundry business) and delivered it five months late. The claimants claimed for:
graph TD
A["Loss caused by<br/>breach of contract"] --> B{"Is the loss<br/>too REMOTE?"}
B --> C["LIMB 1:<br/>Arising NATURALLY<br/>from the breach?<br/>(Ordinary course of things)"]
B --> D["LIMB 2:<br/>In the REASONABLE<br/>CONTEMPLATION of both<br/>parties at time of contracting?<br/>(Special knowledge)"]
C -->|"Yes"| E["Loss is RECOVERABLE"]
C -->|"No"| D
D -->|"Yes — defendant<br/>had special knowledge"| E
D -->|"No — defendant did<br/>not know"| F["Loss is TOO REMOTE<br/>and NOT recoverable"]
style E fill:#27ae60,color:#fff
style F fill:#e74c3c,color:#fff
The Achilleas [2008]:
The House of Lords considered whether a broader test of "assumption of responsibility" should replace the Hadley v Baxendale test. Lord Hoffmann suggested that the question should be whether the defendant had assumed responsibility for the type of loss in question. However, the majority applied the traditional Hadley v Baxendale test, though some Lords expressed sympathy for the assumption of responsibility approach. The precise scope of the test remains debated.
The innocent party has a duty to take reasonable steps to mitigate (reduce) their loss. They cannot recover for losses that they could reasonably have avoided.
In British Westinghouse Electric and Manufacturing Co Ltd v Underground Electric Railways Co of London Ltd [1912], the claimant was supplied with defective turbines. They replaced them with superior turbines that were more efficient than the contract turbines. Viscount Haldane LC held that the claimant could recover the cost of the replacement turbines but had to give credit for the benefits obtained from the superior replacements. The duty to mitigate is a duty of reasonableness — the innocent party is not required to take extraordinary or unreasonable steps.
Key Principles of Mitigation:
| Principle | Explanation |
|---|---|
| The duty is one of reasonableness | The innocent party is not required to take unreasonable steps |
| The innocent party must not increase their loss | They must not act unreasonably to make the loss worse |
| Successful mitigation reduces the damages award | Credit must be given for benefits obtained through mitigation |
| The burden of proof is on the defendant | The defendant must prove that the claimant failed to mitigate |
In Payzu Ltd v Saunders [1919], a seller wrongfully refused to deliver goods on credit but offered to sell for cash. The buyer refused and bought elsewhere at a higher price. The court held the buyer should have accepted the cash offer — they had failed to mitigate.
Contracting parties may include a clause specifying the amount of damages payable on breach. Such a clause may be either:
| Type | Validity |
|---|---|
| Liquidated damages | A genuine pre-estimate of loss — enforceable |
| Penalty clause | A sum designed to punish or deter breach — unenforceable (the court will award actual damages instead) |
Subscribe to continue reading
Get full access to this lesson and all 10 lessons in this course.